5E Advanced Materials Publishes Fort Cady Project SK-1300 Pre-Feasibility Technical Report with a US$724.8M Pre-Tax NPV7, 19.2% IRR, Initial 39.5-Year Mine Life

Technical Report Underscores Large, Multi-generational
High-Grade Colemanite Deposit to Support Domestic Supply of 
Boron Amid Growing Demand

HESPERIA, CALIFORNIA / ACCESS Newswire / August 7, 2025 / 5E Advanced Materials, Inc. (“5E” or the “Company”) (Nasdaq:FEAM)(ASX:5EA), a boron and lithium company designated as Critical Infrastructure by the U.S. Department of Homeland Security, is developing one of the world’s largest new conventional boron deposits through a vertically integrated platform, is pleased to announce the completion of the Preliminary Feasibility Study (the “Technical Report”) for the Company’s Fort Cady Project (the “Project”) located in the Mojave Desert, near the town of Newberry Springs, California.

The Project underpins 5E’s strategy to become a vertically integrated global supplier of critical and industrial materials through in-situ extraction of colemanite, from which the Company intends to produce boron and calcium-based products which will support global electrification, energy, food security, and critical defense applications.

Highlights of the Pre-Feasibility Study

  • Technical Report is specifically focused on Phase 1 of the Project, converting 41% of the resource into 5.4M tons of boric acid (H3BO3) reserves yielding 39.5-year life of mine

  • Total Mineral Reserves of 5.4M tons boric acid with grade of 8.03% (B2O3)

  • Technical Report ONLY includes Phase 1 production and presents robust economics with forecasted pre-tax net present value (NPV7) of US$724.8 million and 19.2% unlevered IRR

  • Project retains optionality for future expansion phases of additional production tonnage and value-added boron derivatives

  • The initial Phase 1 plant targets delivery of 130,000 tons per year of boric acid production, approximately ~11% of global boric acid demand today

  • Mining permits in place with the colemanite reserve mined using an in-situ leaching (“ISL”) method, thereby minimizing the surface land disturbance required for the Project facilities

  • The expected initial project capital cost (inclusive of a gas COGEN facility) is US$367M for Phase 1 plus US$55M contingency (15%) and US$13M of owner’s cost

  • By-product mix includes calcium chloride and gypsum with expected all-in sustaining cash (including logistics) of US$554.80 per ton of boric acid

  • Market study indicates tight supply with demand forecasted to exceed supply in 2026 driving boric acid prices higher

  • Revenue from production will primarily be derived from boric acid sales, approximately 94% of total revenue, while by-products of calcium chloride and gypsum will provide approximately 6% of total revenue

The Technical Report, which outlines an initial mine life of 39.5 years, confirms the strong economics of an ISL operation that would initially produce 130,000 short tons per year of boric acid along with calcium-based by-products; calcium chloride and gypsum. This Technical Report only includes Phase 1 of the Project, with optionality for phased expansion of additional tonnage and value-added boron derivatives.

The Company commenced mining operations in January 2024 and currently has a small-scale facility (“SSF”) that began operation in April 2024, which has provided invaluable operational data that has been incorporated into the basis of design for the Project. The SSF has achieved a steady state of production for boric acid and gypsum in addition to qualifying 14 customers who have set the stage for continued offtake negotiations. Most recently, two injection-recovery wells were converted to horizontal wells intercepting approximately 3,000 feet of high-grade colemanite.

“This technical report validates the economic strength and strategic importance of the Fort Cady Project,” stated Mr. Paul Weibel, Chief Executive Officer of 5E Advanced Materials. “With strong projected economics underpinned by meticulous technical work, we are now positioned to move into definitive feasibility planning, FEED-engineering and long-term project financing with the right team who have been critical in reaching this point in the development cycle. I am very pleased with 5E’s team and partners work to deliver this report. We have mined and processed for the last 18-months and have qualified product with over 14 large global end users. As we target large-scale commercial production in 2028, we look toward the economic potential of the Project, which we expect will provide high paying jobs in California and be a significant long-term U.S. producer of boron to maintain the security of the boron supply chain in the United States.”

5E will host a conference call to discuss the results of the Technical Report on Tuesday, August 12, 2025, at 5:00 p.m. EDT (2:00 p.m. PDT). The call will be hosted by 6ix with remarks from Mr. Paul Weibel, Chief Executive Officer of 5E Advanced Materials, Inc.

To participate, note the following:

DATE: August 12, 2025
TIME: 5:00 p.m. EDT (7:00 a.m. AEST on August 13, 2025)
LINK:Registration (https://6ix.com/event/5e-advanced-materials-market-update-1)

Details of the Pre-Feasibility Technical Report

The Technical Report summary results are presented in Table 1.

Table 1. Project Summary

Description

Units

Total/Amount

Mine Life

Years

39.5

Reserves B2O3 (tonnage)

Tons (short)

3,003,955

Reserves H3BO3 (tonnage)

Tons (short)

5,335,023

Reserves B2O3 (grade)

%

8.03%

Recovery B2O3 (in-situ)

%

81.9%

Mining Efficiency (drilling)

%

95.0%

Recovery B2O3 (processing)

%

95.1%

Table 1. Project Summary (Continued)

Production

Annual Production (H3BO3)

Tons (short) per year

130,000

Annual Production (Gypsum)

Tons (short) per year

129,000

Annual Production

(CaCl2 ~ 38%)

Tons (short) per year

57,000

Capital Costs

Initial Capital with Contingency

$M USD

435.0

Sustaining Capital

$M USD

39.9

Total Capital (life of mine)

$M USD

474.8

Operating Costs (Full-Run Rate)

Variable Costs

$/t H3BO3

405.7

Fixed Costs

$/t H3BO3

222.1

Credits

$/t H3BO3

(73.0)

Net Total Costs (inclusive of logistics)

$/t H3BO3 (net)

554.8

Economic Analysis

Average Price LOM – H3BO3

$/short ton

1,355

Netback Price – Gypsum

$/short ton

21

Netback Price – CaCl2 ~38%

$/short ton

120

Pre-Tax: Free Cashflow

$M USD

3,749

Pre-Tax: NPV7

$M USD

725

Pre-Tax: IRR

%

19.2

After-Tax: Free Cashflow

$M USD

2,625

After-Tax: NPV7

$M USD

469

After-Tax: IRR

%

15.9

After-Tax: Payback Period

Years

5.9

Project Location

The Project is located halfway between Las Vegas, Nevada and Los Angeles, California and includes both private and federal land. The Project is located approximately 2 miles south of Interstate 40 and approximately 25 miles east of Barstow, California. The site is connected to approximately 1 megawatt of grid power and is approximately 2 miles from major natural gas transmission lines and the BNSF rail line. Figure 1 shows the project location.

Figure 1. Fort Cady Project Location

Mineral Resources

The Technical Report defines both Mineral Resources and Mineral Reserves for the Project. The Mineral Resources on lands under 5E’s mineral control include 23.5 million short tons of Measured ore containing 3.26 million short tons of in-situ boric acid, with an average grade of 7.91% B₂O₃. The Indicated category comprises 85.6 million short tons of ore containing 11.8 million short tons of in-situ boric acid, with an average grade of 7.89% B₂O₃. Mineral resources were estimated using a 2.0% B2O3 cut-off grade and Table 2 summarizes the mineral resources.

Table 2. Fort Cady Project Mineral Resources

*Mineral Resources

Short Tons (MST)

B2O3 (wt. %)

B2O3 (MST)

H3BO3 (MST)

Measured

23.50

7.91

1.84

3.26

Indicated

85.63

7.89

6.66

11.83

Total Measured + Indicated

109.13

7.89

8.50

15.09

Total Inferred

4.26

7.45

0.31

0.55

*Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Under S-K 1300, inferred mineral resources are not considered economically recoverable within the current mine plan and are excluded from the production schedule and economic analysis. Inferred Mineral Resources include areas not currently under mineral tenure control. These are disclosed for transparency but excluded from the mine plan and economic model. The Company makes no assurance that mineral rights to these areas will be secured.

Notes to Mineral Resources:

  1. The Mineral Resources in this estimate were independently prepared, including estimation and classification, by Steven Kerr, P.G., C.P.G, Escalante Geological Services, LLC, and are reported in accordance with the definition for Mineral Resources in S-K 1300.

  2. The Mineral Resources were completed using a gridded seam model with Carlson Mining™ software.

  3. The Mineral Resources are current as of March 10, 2025.

  4. Mineral Resources are constrained assuming in-situ leaching and are reported at a cutoff grade of 2.0% B2O3, assume mineralized horizons exhibit lateral continuity that supports in-situ leaching mining methods and based on exploration data, there is reasonable continuity of colemanite mineralization throughout the deposit, respectively.

  5. Only resources located on lands under current mineral control are reflected in the mine plan and economic analysis.

Mineral Reserves

A detailed mine production plan was developed to support the calculation of Mineral Reserves. The mine plan and wellfield optimization are based on third-party engineering work that incorporated 19 months of actual wellfield performance data from the SSF into the design.

Mineral Reserve assumptions, such as plant efficiency, leaching efficiency, and mining efficiency were taken into consideration to calculate the reserve estimate. The operating costs were derived from material and energy balances as well as a detailed labor build developed from first principles. The following steps and assumptions were used to calculate Mineral Reserves:

  • Measured and Indicated Mineral Resource of fee-based land and the power corridor were used as the base resource and Inferred Resources were excluded.

  • The mine plan includes a Phase 1 plan for which 5E has demonstrated mineral tenure.

  • Trade off analysis of actual vertical well performance relative to expected horizontal well performance can increase colemanite contact up to 20x with extended lateral wells and achieve permeable driven injection rates of +100 gallons per minute.

  • The surface chemical plant would deliver a 95.1% boric acid yield.

  • Leaching efficiency is 81.9% based on leach testing.

  • Solution mining efficiency is 95.0% based on the July 2025 horizontal well drill program.

  • Discounted cash flow incorporated capital and operating cost inputs.

Mineral Reserves are reported in-situ using a 2.0% B2O3 cut-off grade. Table 3 summarizes the Mineral Reserves for the Project.

Table 3. Fort Cady Project Mineral Reserves

Mineral Reserves

Average B2O3 Grade (wt. %)

Recoverable Mineralized Bed Volume (ft3)

B2O3 (MST)

H3BO3 (MST)

Proven

8.03

19,894,414

0.76

1.35

Probable

8.03

58,565,846

2.24

3.98

Total Reserves

8.03

78,460,260

3.00

5.33

Notes to Mineral Reserves:

  1. The Mineral Reserves in this estimate were independently prepared, including estimation and classification, by Alan White, P.E., Miocene, Inc., and are reported in accordance with the definition for Mineral Reserves in S-K 1300.

  2. The Mineral Reserve Estimate is based on a cut-off grade of 2.0% B₂O₃. Mining recovery, mining efficiency, and process recovery factors applied were 81.9%, 95.0% and 95.1%, respectively, based on pilot-scale testing and engineering assumptions outlined in the Pre-Feasibility Study.

  3. Mineral Reserves are a subset of the Measured and Indicated Mineral Resources and do not include Inferred Mineral Resources nor any Mineral Resource for which 5E does not have mineral tenure.

  4. The Mineral Reserves are current as of August 4, 2025.

  5. Rounding, as required by the guidelines, may result in minor summation differences between tons, grade, and contained B2O3 or H3BO3 content.

Mining Method

The Project will be employing in-situ leaching as its mining method to recover borates from the mineralized horizons. The depth and grade of the deposit precludes conventional mining techniques such as open pit and underground mining. With ISL mining, there is no stripping of waste rock or underground development required for the Project. ISL activities include drilling and constructing of injection/recovery wells, installing pumping or airlifting extraction equipment on the wells, and piping to transport barren leach solutions to the wellfield and Pregnant Leach Solution (“PLS”) back to the chemical plant for processing.

Based on the results of operating the SSF injection, recovery wells and work completed by 5E, the Large-scale Boron Facility (“LSBF”) calls for the installation of 27 directional wells targeting the upper mineralized horizon (“UMH”), major mineralized horizon (“MMH”), and lower mineralized horizon (“LMH”) spaced at 200-ft horizontal offset and 120 – 180-ft vertical spacing. The operating strategy of the wells will focus on high-grade mineralization zone cavern development through continuous injection and cyclic push-pull mechanics.

These wells are to operate as injection and recovery wells whereby injection and recovery of lixiviant through separate horizontal wellbores and full reservoir contact is accomplished by geo-steered laterals in a “fishbone” pattern and positively intercepting each well. The leach solution (lixiviant) is pumped into the well and, after a prescribed residence time, is retrieved from the same well, or offset wells as caverns develop, for processing. This method will be used until the dissolution of the colemanite in the deposit progresses to where complete reservoir flow is established between regional groups of wells. Figure 2 details the horizontal well schematic across the deposit.

Figure 2. Fort Cady Wellfield

Processing and Recovery Methods

The processing facility at the LSBF is engineered to support high-efficiency, high-throughput extraction and refinement of boric acid and associated byproducts from the PLS. 5E successfully executed an extensive program of mineral processing and metallurgical testing. Based on these results, the company has selected a proven, crystallization-based process for boric acid extraction. This method has been validated through both laboratory-scale experiments and the operational success of the SSF. The following is a description of the process steps:

  • Solution Mining and Injection: Target minerals are dissolved in-situ using solution mining techniques utilizing heat and steam. The resulting PLS is transported via pipeline infrastructure to the surface processing facilities.

  • PLS Recovery and Clarification: The PLS undergoes pH adjustment through lime addition, which reduces acidity and enables the use of more cost-effective materials of construction. A multi-stage solid-liquid separation process, including filtration, removes precipitated solids, yielding a clarified solution ready for downstream processing.

Figure 3 Planned Site Layout

  • Boric Acid Circuit: This core section of the process is dedicated to the concentration, extraction, and purification of boric acid. A two-stage vacuum chilled crystallization system initiates the precipitation of boric acid, followed by filtration, washing, and redissolution. A second two-stage recrystallization step ensures high-purity product formation. Final dewatering is achieved via centrifugation, and the wet crystals are dried in a rotary dryer, cooled, and packaged. A portion of the centrate is directed to the Impurity Removal Circuit and the remainder is sent to the Gypsum circuit.

  • Impurity Removal Circuit and Evaporation: In the Impurity Removal stage, magnesium hydroxide [Mg(OH)₂] and other impurities are removed from the process stream through a reaction with hydrated lime. This reaction causes the impurities to precipitate, allowing them to be separated via filtration. The filtrate slurry then enters the evaporation circuit, where mechanical evaporators and evaporation ponds precipitate sodium chloride for removal. The concentrated brine, now enriched with calcium chloride (CaCl2), is either directed to truck loading for sale as a byproduct or sent to the Gypsum Circuit for further processing.

  • Gypsum Circuit: The Calcium Chloride rich brine reacts with sulfuric acid to precipitate gypsum, which is then filtered and refined to be sold as a byproduct. This circuit also facilitates the regeneration of hydrochloric acid, which is recycled back to the wellfield for reuse in the mining process.

Infrastructure

The Project is located near Interstate 40 along with nearby access to rail and a natural gas transmission line. Currently, the Project receives approximately 1 megawatt of shore power.

Infrastructure required for the Project is expected to consist of:

  • Natural gas – the Project will require a natural gas pipeline that will need to be connected into a nearby transmission pipeline to serve the processing plant. Discussions are ongoing with a proposal received from the owner of the pipeline and the cost of piping from the Mojave Pipeline to a cogeneration facility (COGEN) included in the capital estimate.

  • Electrical power upgrade – an economic trade-off study is currently being conducted to evaluate co-generation versus an upgraded and dedicated powerline to the Project. The economic analysis in the Technical Report assumes the Project utility is COGEN.

  • Rail – a connection to a rail spur adjacent to the Project is included in the federal permit. Phase 1 logistics contemplate trucking finished product to the customers in the western United States and the Los Angeles ports. Byproducts are expected to be sold in the local California market. Tie-in to rail is expected to be considered for expansion phases of the Project.

  • Roads – Plant access roads will require upgrades, and some roads may require paving. New access roads are also being considered.

  • Water – 5E currently has adequate water resources for Phase 1 of the project with two existing water wells with millsite claims for each well.

  • Material storage – storage for materials products and consumables will need to be built with storage for boric acid and gypsum included in the capital estimate. A calcium chloride load-out station is also included in the capital estimate and is expected to be stored in tanker trucks ready for distribution.

Environmental

In 1990, a Plan of Operations was submitted to the United States Bureau of Land Management (“BLM”) and a Mining Conditional Use Permit and Reclamation Plan was submitted to San Bernardino County, which triggered environmental review under the National Environmental Policy Act (“NEPA”) and the California Environmental Quality Act (“CEQA”). The BLM and San Bernardino County prepared a joint Environmental Impact Statement (“EIS”) and Environmental Impact Report (“EIR”) to satisfy their environmental review requirements under NEPA and CEQA. In 1994, the EIS and EIR process resulted in the issuance of a Record of Decision from the BLM that approved the Plan of Operations and approval of the Mining Condition Use Permit and Reclamation Plan from San Bernardino County. The Project is permitted to produce 90,000 short tons per year of borates, defined as boron oxide or boron oxide equivalent, thus permitting up to approximately 160,000 short tons of boric acid.

In 2020, a Class 3 Underground Injection Control (“UIC”) permit was issued by the United States Environmental Protection Agency (“EPA”). The EPA retains primacy for Class 3 solution mining UIC permits. In November 2023, the EPA approved the commencement of mining operations under this permit. These regulatory approvals form the foundation for Phase 1 development, which aligns with the previously authorized project scope.

Capital Costs

The Technical Report Summary for the Project has been successfully completed by Engineering, Procurement, and Construction Management company Fluor Corporation, Petroleum Engineering and Operating Services company Miocene, Inc., along with collaboration with Ad Infinitum, an engineering firm specializing in chemical process design. An AACE Class 4 estimate capital cost estimate (± 25%) has been prepared. The AACE Class 4 capital estimate covers the period from Front End Engineering Design engineering to first production and is reported in real dollars.

Capital cost expectations for a 130,000 short ton per annum boric acid plant (inclusive of co-product processing and COGEN power) were determined to be $367M for the first stage plus a contingency of $55M and owner’s cost estimate of $13M for a total capital estimate of $435M. Table 4 outlines the capital cost estimate, including initial development costs and a conservative provision for sustaining capital, based on solution mining-specific assumptions, including periodic wellfield expansion, re-drilling, and maintenance costs over the life of mine.

Table 4. Capital Cost Estimate

Scope

Capital Cost (USD Millions)

Process Facility

$280.7

COGEN

$50.2

Wellfield

$30.8

Evaporation Ponds

$5.6

Sub-total

$367.3

Contingency

$55.1

Owner’s Cost

$12.5

Total Capital

$434.9

Operating Costs

Operating costs for the project are segregated into Variable, Fixed, and Other operating costs and are based on detailed material and energy balances provided by Fluor Corporation and a principles first labor build-up. Variable operating costs include packaging, logistics, and raw materials such as natural gas, hydrochloric acid, sulfuric acid, and lime. Fixed operating costs include administrative labor, operating labor, general and administrative overhead, repair labor, repair materials, as well as taxes and insurance. Other operating costs include disposal costs of metals impurities offset with byproduct credits from gypsum and calcium chloride. Table 5 summarizes the operating cost by production phase.

Table 5. Operating Cost

Operating Costs (Full-Run Rate)

Variable Costs

$/t H3BO3

405.7

Fixed Costs

$/t H3BO3

222.1

Credits

$/t H3BO3

(73.0)

Total Costs (inclusive of logistics)

$/t H3BO3 (net)

554.8

Figure 4. Operating Cost Breakdown

Economic Analysis

The Project economics were evaluated using a discounted cashflow analysis based on annual cashflows for the life of the project. The financial model was prepared on an annual basis from the mineral reserve effective date to the exhaustion of mineral reserves for the current mining plan. Mine life can be extended and the Project has additional resources that can be converted to additional mineral reserves with expansion of the wellfield or mine plan in the future. The financial model results are presented in real U.S. dollars.

As with the capital and operating forecasts, the economic analysis is inherently a forward-looking exercise. These estimates rely upon a range of assumptions and forecasts that are subject to change depending upon macroeconomic conditions, operating strategy and new data collected through operation of the SSF. Table 6 summarizes the economic results and Figure 5 highlights project cashflows during the first 15 years.

Table 6. Economic Analysis Summary

Description

Units

Total/Amount

Average Price LOM – H3BO3

$ / short ton

1,355

Netback Price – Gypsum

$ / short ton

21

Netback Price – CaCl2

$ / short ton

120

Pre-Tax: Free Cashflow

$M USD

3,749

Pre-Tax: NPV7

$M USD

725

Pre-Tax: IRR

%

19.2

After-Tax: Free Cashflow

$M USD

2,625

After-Tax: NPV7

$M USD

469

After-Tax: IRR

%

15.9

After-Tax: Payback Period

years

5.9

Figure 5. Cashflow Profile by Year

Financial Model Sensitivity

Sensitivity analysis for the financial model was performed based on changes to boric acid price, annual production, discount rate, variable cost pricing, gypsum price, labor cost per person, and raw material acid utilization. Using a ±10% change for each variable, NPV7 is plotted in real dollars for comparison and arranged in order of total variability.

Figure 6. Economic Sensitivity

Qualified Persons

The Technical Report, entitled “Preliminary Feasibility Report & Technical Report Summary, 5E Advanced Materials Fort Cady Project,” dated August 7, 2025, was prepared in accordance with the Securities and Exchange Commission S-K regulations, Title 17, Part 229, Items 601 and 1300 through 1305. The Technical Report was prepared by the following firms and persons: Miocene, Inc., Fluor Corporation, Geomega, Inc., Escalante Geological Services, LLC and Mr. Paul Weibel. With the exception of Mr. Weibel, who serves as the Company’s Chief Executive Officer, none of the qualified persons is affiliated with the Company or any other entity that has an ownership, royalty, or other interest in the property.

The Technical Report will be available on the U.S. Securities and Exchange’s EDGAR website as an Exhibit 96.1 to the Current Report on Form 8-K filed by the Company on August 7, 2025, in connection with this news release. The Technical Report includes relevant information regarding the assumptions, parameters, and methods used for the Mineral Resource and Mineral Reserve estimates for the Fort Cady Project, as well as information regarding data verification, exploration procedures, and other matters relevant to the scientific and technical disclosure contained in this news release.

Other disclosures of a scientific or technical nature included in this news release regarding the Fort Cady Project have been reviewed, verified, and approved by Mr. Paul Weibel, Chief Executive Officer of 5E Advanced Materials, Inc. who is a Qualified Person as defined by Regulation S-K, Subpart 1300 promulgated by the U.S. Securities and Exchange Commission. Mr. Weibel is responsible for reviewing information related to market strategy, product pricing, and economic assumptions.’

The complete Technical Report titled “Preliminary Feasibility Report & Technical Report Summary, 5E Advanced Materials Fort Cady Project” is available on EDGAR as Exhibit 96.1 to the Company’s Current Report on Form 8-K filed on August 7, 2025. It is also available on the Company’s website – HERE.

About 5E Advanced Materials, Inc.

5E Advanced Materials, Inc. (Nasdaq: FEAM) (ASX:5EA) is focused on becoming a vertically integrated global leader and supplier of boron specialty and advanced materials, complemented by lithium co-product production. The Company’s mission is to become a supplier of these critical materials to industries addressing global decarbonization, food and domestic security. Boron and lithium products will target applications in the fields of electric transportation, clean energy infrastructure, such as solar and wind power, fertilizers, and domestic security. The business strategy and objectives are to develop capabilities ranging from upstream extraction and product sales of boric acid, lithium carbonate and potentially other co-products, to downstream boron advanced material processing and development. The business is based on our large domestic boron and lithium resource, which is located in Southern California and designated as Critical Infrastructure by the Department of Homeland Security’s Cybersecurity and Infrastructure Security Agency.

Forward Looking Statements

This press release includes “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995, as amended. All statements other than statements of historical fact included in this press release should be considered forward looking statements, including without limitation statements regarding the Project’s capital and operating costs; cash costs to produce boron and its related byproducts, as well as estimated contingencies; projected future pricing for boric acid and its related byproducts; the forecasted net present value; projected production volumes and revenues; anticipated cash flows; anticipated cut-off grade and recovery rates; the proposed design of the commercial scale facility; the timing of large-scale commercial production; construction timelines; ability to maintain and modify permits; infrastructure needs; environmental impacts; potential to successfully finance the company and the proposed commercial scale facility; anticipated market value and demand for boric acid, calcium chloride and gypsum; potential technology solutions; anticipated use of land and water; potential for expansion of mineral resources; mineral resource and reserve estimates and assumptions; the potential for future phases of the Project; availability of energy to operate the facility; the economic potential of the Project; and our ability to produce boron and its related byproducts. When used in this press release, the words “believe,” “project,” “expect,” “anticipate,” “estimate,” “intend,” “budget,” “target,” “aim,” “strategy,” “plan,” “guidance,” “outlook,” “intent,” “may,” “should,” “could,” “will,” “would,” “will be,” “will continue,” “will likely result,” and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain such identifying words. These forward-looking statements are based on the Company’s current expectations and assumptions about future events and are based on currently available information as to the outcome and timing of future events. We caution you that these forward-looking statements are subject to all of the risks and uncertainties, most of which are difficult to predict and many of which are beyond our control, incident to the extraction of the critical materials we intend to produce and advanced materials production and development. These risks include, but are not limited to: our ultimate ability to satisfy all customer qualification criteria and achieve commercial offtake agreements, our limited operating history in the borates and lithium industries and no revenue from our proposed extraction operations at our properties; our need for substantial additional financing to execute our business plan and our ability to access capital and the financial markets; our status as an exploration stage company dependent on a single project with no known Regulation S-K 1300 mineral reserves and the inherent uncertainty in estimates of mineral resources; our lack of history in mineral production and the significant risks associated with achieving our business strategies, including our downstream processing ambitions; our incurrence of significant net operating losses to date and plans to incur continued losses for the foreseeable future; risks and uncertainties relating to the development of the Fort Cady project, including our ability to timely and successfully complete our proposed Commercial Scale Boron Facility; our ability to obtain, maintain and renew required governmental permits for our development activities, including satisfying all mandated conditions to any such permits; the implementation of and expected benefits from certain reduced spending measures; the impact of changes in U.S. trade policies and the imposition of tariffs; and other risks and uncertainties set forth in our filings with the U.S. Securities and Exchange Commission from time to time. Should one or more of these risks or uncertainties occur, or should underlying assumptions prove incorrect, our actual results and plans could differ materially from those expressed in any forward-looking statements. No representation or warranty (express or implied) is made as to, and no reliance should be placed on any information, including projections, estimates, targets, and opinions contained herein, and no liability whatsoever is accepted as to any errors, omissions, or misstatements contained herein. You are cautioned not to place undue reliance on any forward-looking statements, which speak only as to the date of this press release.

For additional information regarding these various factors, you should carefully review the risk factors, uncertainties and other disclosures in the Company’s Form 10-K filed on September 9, 2024, as updated by the Company’s Form 10-Q filed on May 15, 2025, and subsequent filings with the U.S. Securities and Exchange Commission throughout the year, as well as in its filings under the Australian Securities Exchange. Any forward-looking statements are given only as of the date hereof. Except as required by law, 5E expressly disclaims any obligation to update or revise any such forward-looking statements. Additionally, 5E undertakes no obligation to comment on third party analyses or statements regarding 5E’s actual or expected financial or operating results or its securities.

For further information contact:

Michael MacMillan or Paola Ashton
PRA Communications
team@pracommunications.com
Ph: +1 (604) 681-1407

SOURCE: 5E Advanced Materials, Inc.

View the original press release on ACCESS Newswire

The post 5E Advanced Materials Publishes Fort Cady Project SK-1300 Pre-Feasibility Technical Report with a US$724.8M Pre-Tax NPV7, 19.2% IRR, Initial 39.5-Year Mine Life appeared first on DA80 Hub.

Information contained on this page is provided by an independent third-party content provider. XPRMedia and this Site make no warranties or representations in connection therewith. If you are affiliated with this page and would like it removed please contact pressreleases@xpr.media

StephenTwomey.com Publishes New Insight on Private Equity Real Estate for Accredited Investors

StephenTwomey.com Publishes New Insight on Private Equity Real Estate for Accredited Investors

Garfield Township, Michigan – October 29, 2025 – PRESSADVANTAGE – Stephen Twomey has released an in-depth resource exploring how accredited investors can strategically participate in…

November 1, 2025

Elite Auto Works Highlights Growing Demand for Advanced Ceramic Coating Technology in Vehicle Protection

Elite Auto Works Highlights Growing Demand for Advanced Ceramic Coating Technology in Vehicle Protection

GRANITE BAY, CA – October 29, 2025 – PRESSADVANTAGE – Elite Auto Works, a Granite Bay-based automotive care specialist, reports increased interest from drivers seeking…

November 1, 2025

Mindmachines.com Advances Mind Machine Technology with Enhanced ROSHIWave Protocols for Meditation and Performance

Mindmachines.com Advances Mind Machine Technology with Enhanced ROSHIWave Protocols for Meditation and Performance

October 30, 2025 – PRESSADVANTAGE – Mindmachines.com has expanded the capabilities of its ROSHIWave IN-SIGHT Mind Machine with advanced brainwave disentrainment protocols designed to help…

November 1, 2025

Blue Interactive Agency Pioneers the Future of Digital Growth With AI-Powered Marketing Solutions

Blue Interactive Agency Pioneers the Future of Digital Growth With AI-Powered Marketing Solutions

Fort Lauderdale, Florida – October 29, 2025 – PRESSADVANTAGE – Blue Interactive Agency, an established leader in digital marketing innovation, is establishing a new standard…

November 1, 2025

OneClickDIY Launches Educational Initiative for DIY Spray Foam Insulation Projects

OneClickDIY Launches Educational Initiative for DIY Spray Foam Insulation Projects

Chantilly, Virginia – October 29, 2025 – PRESSADVANTAGE – OneClickDIY, the authorized distributor of insulation and sealant products, announced the launch of a comprehensive educational…

November 1, 2025

Thailand Privilege Enhances Support for Digital Nomad Visa Seekers Amid Rise in Remote Work

Thailand Privilege Enhances Support for Digital Nomad Visa Seekers Amid Rise in Remote Work

BANGKOK, Thailand – October 30, 2025 – PRESSADVANTAGE – Thailand Privilege has announced expanded consultation services to meet growing demand from remote professionals seeking long-term…

November 1, 2025

TaxFree RV Announces Expanded Registration Services as Motorhome Sales Drive Demand

TaxFree RV Announces Expanded Registration Services as Motorhome Sales Drive Demand

RED LODGE, MT – October 29, 2025 – PRESSADVANTAGE – TaxFree RV, a Montana-based vehicle registration specialist operating since 2005, announced today the expansion of…

November 1, 2025

American Home Quotes Expands Access to Qualified Electricians Through Streamlined Consumer-to-Contractor Connections

American Home Quotes Expands Access to Qualified Electricians Through Streamlined Consumer-to-Contractor Connections

Fort Lauderdale, Florida – October 30, 2025 – PRESSADVANTAGE – As homeowners increasingly depend on modern electrical systems to power smart technologies and energy-efficient appliances,…

November 1, 2025

Hyperke Reveals How to Get Products Stocked at Retail Stores Through Automated Wholesale Expansion Program

Hyperke Reveals How to Get Products Stocked at Retail Stores Through Automated Wholesale Expansion Program

SHERIDAN, WY – October 29, 2025 – PRESSADVANTAGE – Hyperke Growth Partners has released detailed case study results demonstrating how direct-to-consumer brands can secure hundreds…

November 1, 2025

Ornate Home Expands Showroom to Address North Carolina Sleep Health Crisis

Ornate Home Expands Showroom to Address North Carolina Sleep Health Crisis

CHARLOTTE, NC – October 29, 2025 – PRESSADVANTAGE – Ornate Home has expanded its Charlotte showroom to feature an extensive selection of mattresses and pillows…

November 1, 2025

Pilgrim Pest Professionals Completes Training at PestWorld 2025

Pilgrim Pest Professionals Completes Training at PestWorld 2025

Plymouth, Massachusetts – October 29, 2025 – PRESSADVANTAGE – Pilgrim Pest Professionals today announced that members of its field and management team attended PestWorld 2025…

November 1, 2025

Local Businesses Win Big with Press Advantage’s Geo-Targeted PR Distribution

Local Businesses Win Big with Press Advantage’s Geo-Targeted PR Distribution

Las Vegas, NV – October 29, 2025 – PRESSADVANTAGE – Press Advantage, a leading press release distribution service, has announced enhancements to its geo-targeted distribution…

November 1, 2025

Home Multi Gym Exercise Equipment Sale Announced by Strongway Gym Supplies

Home Multi Gym Exercise Equipment Sale Announced by Strongway Gym Supplies

Coventry, UK – October 29, 2025 – PRESSADVANTAGE – Strongway Gym Supplies has announced the sale of its multifunctional home gym range, extending access to…

November 1, 2025

The Organized Millennial Expands Personalized Home Organizer Services

The Organized Millennial Expands Personalized Home Organizer Services

October 29, 2025 – PRESSADVANTAGE – The Organized Millennial, a professional home organization company, has expanded its services to offer enhanced personalized organization solutions for…

November 1, 2025

Time Off Editing Announces New Real Estate Photo Editing Service Line

Time Off Editing Announces New Real Estate Photo Editing Service Line

Los Angeles, California – October 29, 2025 – PRESSADVANTAGE – Time Off Editing has revealed the launch of its specialised Real Estate Photo Editing service,…

November 1, 2025

Dentures Dentist East Dulwich Announces Consultations at The Gardens Dental Centre (Smile 4 U)

Dentures Dentist East Dulwich Announces Consultations at The Gardens Dental Centre (Smile 4 U)

London, England – October 30, 2025 – PRESSADVANTAGE – The Gardens Dental Centre (Smile 4 U) has announced that it is now offering consultations for…

November 1, 2025

Northwest Plumbing Heating & AC Expands Winter Plumber Service Programs for Quad Cities Residents

Northwest Plumbing Heating & AC Expands Winter Plumber Service Programs for Quad Cities Residents

DAVENPORT, IA – October 29, 2025 – PRESSADVANTAGE – Northwest Plumbing Heating & AC has expanded its seasonal maintenance programs and repair services to address…

November 1, 2025

Perla Images Announces Office Relocation to Better Serve Clients

Perla Images Announces Office Relocation to Better Serve Clients

HYANNIS, MA – October 30, 2025 – PRESSADVANTAGE – Perla Images Cape Cod Wedding Photographer today announced the relocation of its primary office to 100…

November 1, 2025

Coventry Emergency Dentist Appointments Now Available at Light Lane Dental Practice

Coventry Emergency Dentist Appointments Now Available at Light Lane Dental Practice

COVENTRY, UK – October 29, 2025 – PRESSADVANTAGE – Light Lane Dental Practice has announced the availability of emergency dentist appointments in Coventry, offering patients…

November 1, 2025

Elite Auto Works Advances Paint Protection Film Technology for Performance and Luxury Vehicles

Elite Auto Works Advances Paint Protection Film Technology for Performance and Luxury Vehicles

GRANITE BAY, CA – October 29, 2025 – PRESSADVANTAGE – Elite Auto Works, a Sacramento-area automotive care specialist, is implementing advanced paint protection film installation…

November 1, 2025

Hannah Restoration Expands Local Services to Better Serve Customers

Hannah Restoration Expands Local Services to Better Serve Customers

HENDERSONVILLE, TN – October 29, 2025 – PRESSADVANTAGE – Hannah Restoration, a family-owned disaster cleanup company serving Middle Tennessee for over 30 years, has expanded…

November 1, 2025

Fence and Deck Depot Announces Flexible Financing Options for Fall Deck Construction Projects

Fence and Deck Depot Announces Flexible Financing Options for Fall Deck Construction Projects

ST. CHARLES, MO – October 29, 2025 – PRESSADVANTAGE – Fence and Deck Depot, a leading deck and fence contractor serving the St. Charles area,…

November 1, 2025

StephenTwomey.com Publishes New Resource: The Ultimate Glossary of Hedge Fund, Private Equity & Alternative Investment Terms (2025 Guide)

StephenTwomey.com Publishes New Resource: The Ultimate Glossary of Hedge Fund, Private Equity & Alternative Investment Terms (2025 Guide)

Garfield Township, Michigan – October 27, 2025 – PRESSADVANTAGE – StephenTwomey.com has released a new educational resource titled “The Ultimate Glossary of Hedge Fund, Private…

November 1, 2025

BeyondStyle Launches AI Image Search for Shopping to Transform How Consumers Find Top Deals

BeyondStyle Launches AI Image Search for Shopping to Transform How Consumers Find Top Deals

Sunnyvale, CA – October 29, 2025 – PRESSADVANTAGE – BeyondStyle, the AI-powered shopping platform developed by BorderX Lab, today announced the launch of its AI…

November 1, 2025

S & J Printing Expands Custom Business Apparel Printing for Local Companies

S & J Printing Expands Custom Business Apparel Printing for Local Companies

Doctors Inlet, Florida – October 29, 2025 – PRESSADVANTAGE – S & J Printing, a screen printing company based in Orange Park, Florida, has expanded…

November 1, 2025

Hoffman Concrete Contractors Adds Concrete Resurfacing to Service Lineup

Hoffman Concrete Contractors Adds Concrete Resurfacing to Service Lineup

October 30, 2025 – PRESSADVANTAGE – Hoffman Concrete Contractors has announced the addition of concrete resurfacing to its service lineup, expanding its offerings for residential…

November 1, 2025

netpulse AG Advances AI-Powered Advertising Solutions for Switzerland’s Digital Marketing Sector

netpulse AG Advances AI-Powered Advertising Solutions for Switzerland’s Digital Marketing Sector

Winterthur, ZH – October 29, 2025 – PRESSADVANTAGE – netpulse AG, a Swiss digital marketing agency specializing in Google Ads, SEO, and social media marketing,…

November 1, 2025

All In Solutions Counseling Center Strengthens Alumni Support Network to Foster Long-Term Recovery

All In Solutions Counseling Center Strengthens Alumni Support Network to Foster Long-Term Recovery

BOYNTON BEACH, FL – October 29, 2025 – PRESSADVANTAGE – All In Solutions Counseling Center has enhanced its comprehensive alumni support program to provide ongoing…

November 1, 2025

The Wedding Planner Hong Kong Expands Event Planning Capabilities to Strengthen Professional Coordination Standards

The Wedding Planner Hong Kong Expands Event Planning Capabilities to Strengthen Professional Coordination Standards

HONG KONG, HK – October 29, 2025 – PRESSADVANTAGE – The Wedding Planner Hong Kong has announced the continued advancement of its event planning division,…

November 1, 2025

Goldstrom Partners with SMX to Deliver End-to-End Traceability and Circularity in Precious Metals

Goldstrom Partners with SMX to Deliver End-to-End Traceability and Circularity in Precious Metals

NEW YORK, NY AND SINGAPORE, SG AND DUBAI, UAE / ACCESS Newswire / October 29, 2025 / SMX (Security Matters) PLC (NASDAQ:SMX), a global leader…

November 1, 2025

Metiss and Solar Rescue Announce Merger to Power the Next Evolution in Solar Intelligence

Metiss and Solar Rescue Announce Merger to Power the Next Evolution in Solar Intelligence

AI-powered merger creates the first integrated solar platform combining advanced analytics and field service for real-time energy optimization and transparency. SEATTLE, WA / ACCESS Newswire…

November 1, 2025

Delivery Updates, Your Way: Dispatch Launches Customizable Notifications

Delivery Updates, Your Way: Dispatch Launches Customizable Notifications

The new feature gives customers control over which updates they receive and how they receive them. BLOOMINGTON, MINNESOTA / ACCESS Newswire / October 29, 2025…

November 1, 2025

SMX and trueGold Transform the Gold Supply Chain Into a Market of Verified Value (NASDAQ: SMX)

SMX and trueGold Transform the Gold Supply Chain Into a Market of Verified Value (NASDAQ: SMX)

NEW YORK, NY / ACCESS Newswire / October 29, 2025 / Gold has always symbolized permanence, wealth, and beauty. What it has never offered is…

November 1, 2025

Maxon Strengthens Growth Strategy with Appointment of Ksenia Kolchina as Vice President of Marketing

Maxon Strengthens Growth Strategy with Appointment of Ksenia Kolchina as Vice President of Marketing

Kolchina joins to drive Maxon’s growth vision, fueling expansion into new industries and markets while reinforcing the company’s creative foundation. BAD HOMBURG, GERMANY / ACCESS…

November 1, 2025

Revelation Biosciences Inc. Announces Cancellation of Adjournment of October 29, 2025 Special Meeting of Stockholders and New Record Date

Revelation Biosciences Inc. Announces Cancellation of Adjournment of October 29, 2025 Special Meeting of Stockholders and New Record Date

SAN DIEGO, CA / ACCESS Newswire / October 29, 2025 / Revelation Biosciences, Inc. (NASDAQ:REVB) (the “Company” or “Revelation”), a clinical-stage life sciences company focused…

November 1, 2025

Money Metals Expands Fractional Gold Lineup, Lowering the Barrier to Real Gold Ownership

Money Metals Expands Fractional Gold Lineup, Lowering the Barrier to Real Gold Ownership

EAGLE, IDAHO / ACCESS Newswire / October 29, 2025 / Money Metals announced an expanded selection of fractional gold coins, rounds, bars, and other items…

November 1, 2025

Certified Asbestos Removal & Restoration Inc. Recognized With 2025 Consumer Choice Award for Asbestos Removal in Southern Alberta

Certified Asbestos Removal & Restoration Inc. Recognized With 2025 Consumer Choice Award for Asbestos Removal in Southern Alberta

CALGARY, AB / ACCESS Newswire / October 29, 2025 / Certified Asbestos Removal & Restoration Inc., a trusted leader in environmental hazard remediation, has been…

November 1, 2025

Four Winners Announced for the 2025 Mass Timber Competition: Building Sustainable Schools

Four Winners Announced for the 2025 Mass Timber Competition: Building Sustainable Schools

OREGON CITY, OREGON / ACCESS Newswire / October 29, 2025 / The Softwood Lumber Board (SLB) and the USDA Forest Service (USDA) announced the winners…

November 1, 2025

ePropelled Expands Its GPM Series for UGVs. Intelligent Integrated Drive Systems Deliver Scalable Power, Efficiency, and Control

ePropelled Expands Its GPM Series for UGVs. Intelligent Integrated Drive Systems Deliver Scalable Power, Efficiency, and Control

New GPM35, GPM50, and GPM70 Combine Integrated Motors, Controllers, and Gearboxes to Power Next-Generation Unmanned Ground Vehicles LACONIA, NH / ACCESS Newswire / October 29,…

November 1, 2025

Alberta Furnace Cleaning Recognized With 2025 Consumer Choice Award for Furnace and Duct Cleaners in Southern Alberta

Alberta Furnace Cleaning Recognized With 2025 Consumer Choice Award for Furnace and Duct Cleaners in Southern Alberta

CALGARY, AB / ACCESS Newswire / October 29, 2025 / Alberta Furnace Cleaning, a Calgary-owned and operated company serving Albertans since 1986, has been recognized…

November 1, 2025